In August 1926, a federal survey crew worked the Mississippi River below St. Paul with seine nets, station by station, haul by haul, counting fish. Their report, written by A. H. Wiebe of the U.S. Bureau of Fisheries, is this story’s primary source, and its count is stark. Between St. Paul and Hastings, the nets turned up one stickleback, about an inch and a half long, and one short-nosed gar. On August 19, across four hauls between those two cities, the report says plainly: not a single fish was taken. The river below the Twin Cities had not gone empty by accident. It had been used, for decades, as the cities’ sewer.
For decades, Minneapolis and St. Paul sent their sewage into the Mississippi untreated, and by 1926 a federal survey could find almost nothing alive in it: one stickleback and one gar between St. Paul and Hastings. The answer was a treatment plant on Pig’s Eye Island, dedicated in May 1938 and in service that summer. It was the first major sewage treatment plant serving a big metropolitan area on the Mississippi River, and the river it began cleaning is still being cleaned by its successor today.
The river before the plant
City sewers began replacing backyard disposal in the 1870s, but the sewers emptied straight into the river. Wiebe’s 1926 report says the Twin Cities’ sewage and industrial waste were dumped without previous treatment, and Minneapolis’s own history notes floating islands of sewage in 1930.
The river’s shape worked against it. In 1917 the new lock and dam below Minneapolis, today’s Lock and Dam No. 1 (later called the Ford Dam), slowed the river, and sewage solids began to settle behind it. By the early 1920s the estimate was three million cubic yards of sewage sludge sitting in the pool above the dam. The State Board of Health declared the river a public-health nuisance, and its formal findings called the river a menace to public health as far south as Lake Pepin. In 1923 the State Board of Health warned both cities; the letters went unanswered. The Board wrote again in 1925. People downstream, and conservationists in Minnesota and Wisconsin, pressed the cities to stop. What finally moved the two cities was not a letter. It was a new district, created by the state in 1933 with the legal power to build.
A whiskey seller’s name
The plant’s odd name is older than the city it serves. Pierre “Pig’s Eye” Parrant had been around Fort Snelling since about 1832; in 1838 he staked a claim at Fountain Cave, on the river below today’s downtown St. Paul. He sold whiskey from a shack at the mouth of Fountain Cave, then from a tavern near today’s downtown, a shack often called the first building in what became St. Paul. In 1839, a man staying at Parrant’s tavern dated a letter home “at Pig’s Eye,” as a joke, and the name stuck; mail began arriving addressed to Pig’s Eye. In 1841 Father Lucien Galtier dedicated a log chapel to St. Paul, and the name soon replaced Pig’s Eye for the settlement. But the lake and island downriver still carry Parrant’s nickname, and from the start the plant was known by the island it stood on. Officially it was the Sanitary District’s treatment plant; most people called it the Pig’s Eye plant, after the island it stands on.
The build
In 1933 the state created the Minneapolis-St. Paul Sanitary District, under Chapter 341 of that year’s laws, taking over from the Metropolitan Drainage Commission. In early 1934, the federal Public Works Administration agreed to $16 million in grants and loans. Sewer tunnel work began in July 1934; construction of the plant itself began in 1935. Engineers of the Drainage Commission and then the Sanitary District planned the system, and the District built it, with James A. Childs, the Drainage Commission’s first chief engineer, remembered as the driving force behind the plan and the choice of the Pig’s Eye site. About 52 miles of interceptor sewers, most of them tunneled, were built between 1934 and the plant’s 1938 opening, much of the tunneling done by sandhogs. The plant was designed to treat an average flow of 134 million gallons a day.
Summer of 1938
Dedicated in May 1938, the plant went into service that summer. Its chief engineer, George J. Schroepfer, later wrote that it began operating on June 1, 1938, and that is the closest thing to a primary date the record holds. It was a primary plant: screens and grit chambers, big settling tanks, chlorine to kill bacteria, and furnaces to burn the sludge. The change came fast. By the Metropolitan Council’s own anniversary account, the floating mats of sludge and scum were gone within four months, and fish, walleye among them, returned within two years. Growth had overloaded the plant again by the mid-1960s, which is the honest shape of the story: the plant ended the worst era, and then the cities had to keep building.
The river came over the dike
Pig’s Eye Island sits about 12 feet above normal river level, and the dike around the plant was built to hold back the 1881 flood crest of about 702 feet. In 1952, 1965 and 1969 the river rose above the 1881 mark the dike was built for; 1965 was the worst. That April the plant shut down on April 8 as the river rose three feet a day. Entrances were sandbagged, cots and a commissary were set up inside, and office staff moved to St. Paul City Hall. A 41-man crew was cut off and stayed 12 days. Water came over the dike on April 12, the river crested at 708.5 feet on April 16, and after three weeks of cleanup the plant was back in operation on May 9. A higher dike and floodwall, built to 716 feet, were finished in 1975.
Next door is a separate site, the Pig’s Eye Dump, an unpermitted city dump from the 1950s to 1972 that is now a state Superfund site. It is not part of the plant, and the plant is not the source of it. The one link between them is exact: from 1977 to 1985, the plant’s sewage sludge ash was placed on about 31 acres of the dump site under a state permit.
The plant today
The District gave way to a regional sewer agency in 1970, and since 1994 the Metropolitan Council has run the plant. Its current official name is the Metropolitan Water Resource Recovery Facility, though the Council also calls it the Metro Plant. By the Council’s figures it serves about 1.8 million people in 66 communities, treats an average of about 170 million gallons a day, and is Minnesota’s largest wastewater treatment plant. The island plant that Parrant’s nickname christened is still doing the work it was built for in the summer of 1938.
Where the past meets the present
The 1926 survey is worth keeping because it is a measurement, not a memory. Before a city can argue about how to save a river, someone has to go out with nets and write down what is actually in it, haul by haul, even when the answer is almost nothing.
Carry this with you: two fish, honestly counted, can move two cities further than a generation of complaints. What does a river look like the year before a city decides to save it?
Sources
A. H. Wiebe, U.S. Bureau of Fisheries, “Biological Survey of the Upper Mississippi River, with Special Reference to Pollution” (survey of August and September 1926), Bulletin of the Bureau of Fisheries.
Metropolitan Waste Control Commission, “The MWCC and the Mississippi: 50 Years of Stewardship” (1988), Minnesota Legislative Reference Library copy: https://www.lrl.mn.gov/docs/2015/other/150135.pdf
Minnesota State Board of Health, findings and order creating the Minneapolis-St. Paul Sanitary District under Chapter 341, Laws of Minnesota for 1933: https://www.lrl.mn.gov/archive/sos/film/pdf/6112.pdf
George J. Schroepfer, “Experiences in Operating a Chemical-Mechanical Sewage Treatment Plant,” Transactions of the American Society of Civil Engineers, vol. 107 (1942), abstract: https://ascelibrary.com/doi/10.1061/TACEAT.0005532
Minnesota Department of Health, Waterline feature, “Metro Plant.”
Metropolitan Council, “Metropolitan Water Resource Recovery Facility” facility page; “100+ Years of Water Quality Improvements in the Twin Cities” brochure; and “Floods at Pigs Eye Island” (March 21, 2019), drawn from the MWCC’s 1988 anniversary history.
Ronald M. Hubbs, Ramsey County History 26:3 (Fall 1991), on Pierre “Pig’s Eye” Parrant and the Fountain Cave claim.
MNopedia, “This Day in Minnesota History,” June 2, 1838, and November 1, 1841.
National Park Service, “River of History” (John O. Anfinson), chapter 8 and Epilogue, and “Fountain Cave.”
City of Minneapolis, “History of stormwater and wastewater in Minneapolis.”
Minnesota Pollution Control Agency, “St. Paul Pig’s Eye Dump site.”
Enjoyed this story?
Get one like it every week — plus our free 10 Turning Points timeline.